A Liebherr MK 88-4.1 mobile construction crane, supplied by the Ponticelli group of companies, has repaired a historic bridge in central Paris and reinstalled a damaged piece of public artwork, Liebherr reports. Working on the Pont-Neuf, the crane restored sections of 'La Caverne du Pont-Neuf,' an installation by the French artist JR that had been damaged by weather.
The temporary artwork was created as a tribute to the 1985 wrapping of the Pont-Neuf by artists Christo and Jeanne-Claude. Its inflatable structure is roughly 120 metres long. In early June, violent gusts of wind and hail tore parts of the outer shell. According to Liebherr, Ponticelli had a lifting solution under development within hours of the damage.
Louis-Arthur de Quatrebarbes, who heads the handling and lifting agency at Ponticelli, said the team was on site only a few hours after the damage occurred to work out the best technical solution together with the client. He noted that in addition to repairing the tarpaulin, the crew had to carry out a safe lifting operation in almost constant wind and under considerable time pressure.
Working within a crowded landmark
As the oldest bridge in Paris, the Pont-Neuf offers limited working space and receives a large number of daily visitors. The team used load-distribution plates to reduce ground pressure, while safety and traffic management measures were put in place so the operation could be carried out securely.
The crew had initially planned to use a larger Liebherr mobile crane. Because of the tight conditions, the Liebherr MK 88-4.1 was brought in instead. Its 45-metre trolley jib reached all the damaged areas of the structure. A four-axle design allowed the machine to be moved easily from one side of the bridge to the other, where storm damage had also occurred. The short set-up time and compact outrigger system further supported the work.
Night shifts and precision
The crane cab could move at working height, giving the operator a clear view of the roughly 18-metre-high structure and the rope access technicians. Boom-mounted spotlights lit the work area during night-time operations.
The repairs were completed over four night shifts. Damaged fabric sections weighing between 200 and 400 kilograms were lifted and reattached in collaboration with rope access technicians. Because the site sits in a wind corridor along the River Seine, weather conditions were monitored continuously, and the crane operator and rope access technicians stayed in radio contact throughout.
Before work began, the team carried out site inspections, load calculations and collision analyses of the surrounding buildings. A 360-degree test then confirmed the planned crane positioning.
De Quatrebarbes said Ponticelli was proud to have taken part in the work of art, echoing JR's remark that the installation of the artwork is itself part of the artwork — and, he added, so is the crane. He described the visually striking deployment of the MK crane as a magical moment.
Liebherr said the Pont-Neuf deployment demonstrated the MK 88-4.1's strengths in demanding inner-city projects, where heritage conservation, confined spaces and a high level of precision come together. The company positions the mobile construction crane as combining reach, compactness and flexibility.