Helix Construct, a Newbury-based design-and-build contractor, went into administration in September owing £4.8m to suppliers, according to an update at Companies House by administrator KR8 Advisory Limited.
The same update set out £2.3m owed to banks and financiers and £260,000 in outstanding pay to the company’s 35 staff. The three disclosed categories alone total £7.36m. They cover supplier claims, financing claims and employee pay, although the available details do not set out expected recoveries.
Cash and contract concerns
Latest accounts showed that Helix Construct had been under growing cash and profitability pressure. Auditors also raised concerns over the valuation and profit recognition on several contracts.
Those audit concerns relate to how contracts were valued and when profit was recognised. The administration update does not say whether those issues contributed to the failure; it records the creditor position and the background pressure described in the accounts.
Turnover and reporting period
For the 18 months to June 2025, turnover reached £40m. That compares with £21m in the previous 12-month financial year. Because the periods differ in length, the figures are not a direct like-for-like comparison, but they indicate the scale of the contractor’s operations before administration.
The company had been in business since 2017. It specialised in design and build construction for affordable housing, education, care and commercial projects across London and the south of England.
Creditor groups
Supplier debt is the largest category disclosed, at £4.8m. The £2.3m owed to banks and financiers is separate, while the £260,000 in unpaid pay is owed to 35 staff. The update therefore identifies exposure across the contractor’s supply chain, its lenders and its workforce.
The update provides the public debt outline but does not set out expected recoveries for suppliers, lenders or staff. The disclosed figures are therefore a creditor snapshot rather than an outcome.
Helix Construct’s administration follows a period in which its latest accounts pointed to cash and profitability strain. The disclosed debts show that the failure extends beyond suppliers to lenders and employees, with the wage shortfall affecting 35 staff.
The case also illustrates how a design-and-build contractor’s insolvency can leave multiple creditor groups facing uncertainty at once. The available update sets out the amounts owed but does not establish recovery outcomes for any of them.